Guides and resources
How to design an underground eco-island: space, capacity, vehicles and civil works
Designing an underground eco-island: volumes, fractions, layout, traffic, collection vehicles, civil works and emptying systems to define before procurement.
♪ How to design an underground eco-recycling island: space, capacity, means and necessary works
Designing an underground eco-recycling island does not simply mean choosing how many dumpsters put under the road.
The location must work at the same time for those who give the waste, for those who carry out the collection and for those who must take care of maintenance, safety and management over the years.
For this reason the project should start from a precise sequence: users, waste, volumetrics, collecting frequency, means, road, available space, civil works and management mode.
Only after these checks you can choose between basement bells, billboards for loadable bins, stationary bins or other configurations.
In fact, Bunder Waste distinguishes systems with different operating logics: 3, 4 and 5 m3 basement bells, 1100 and 1,700 litre containers with rear loading compactors, 2,400 and 3,200 litres stationary platforms associated with side loading and different semi-internet solutions.
♪ The first decision is not the container: it is the service that must carry out
The starting point should be the real situation of the territory.
A station destined to a stable residential district does not necessarily present the same needs of a station located in a historic centre, near restaurants, in a tourist area or inside a harbour area.
Before defining technology, it is necessary to reconstruct the service provided:
- who will use the station;
- which fractions will be conferred;
- what quantities must be handled;
- all the containers will be emptied;
- which means will carry out the collection;
- where he can stop the medium;
- what operations the operator must perform;
- what constraints exist on the site.
The reason is simple: a basement system is not an independent service equipment.
The same technical documentation of an AMIU Puglia race for the supply and installation of ecological islands buried in Bari treats the intervention as a complex supply, with technical documentation, price list and specific metric compute, as well as laying activities.
Project Checklist: the 12 elements to define
To transform the problem into a specific technique, the project can be developed through twelve audits.
♪ No. | Element | Project question | ♪ | 1 | Users | How many people or activities will they use the post? ♪ | 2 | Type of waste | What fractions should be collected? ♪ | 3 | Volumetria | What capacity is for each fraction? ♪ | 4 | Frequency | Any amount of emptying must be done? ♪ | 5 | Half | Which vehicle will serve the island? ♪ | 6 | Space | How much space is available above and below the country plan? ♪ | 7 | Media access | Can the medium reach and serve the station? ♪ | 8 | Security | How are installation, handling and maintenance managed? ♪ | 9 | Civil Works | What excavations, foundations, structures and restorations are necessary? ♪ | 10 | Finishes | How is the location integrated into the pavement and urban context? ♪ | 11 | Access Control | Do you need to identify or limit users? ♪ | 12 | Monitoring | Do you need to know the filling level or manage operational data? ♪
Not all stations require the same level of technological design. A traditional configuration can have very different needs from an island with access control and data transmission.
--
#1 Number of users: how many conditions do you really need to manage the location?
The number of users is the first quantitative data to be collected, but it is not enough alone.
One must distinguish at least between:
- domestic utilities;
- commercial activities;
- catering;
- accommodation facilities;
- offices;
- other non-domestic utilities;
- seasonal or strongly variable presence.
A condominium with 100 apartments and a group of restaurants with 100 anagraphic users can generate completely different bestowal profiles.
For this reason the sizing should not automatically translate "number of inhabitants" into "number of cubic metres".
It is more useful to build a profile of the post: waiting quantity per fraction, distribution over time and expected collection frequency.
What to collect in preliminary phase
For an existing location it is useful to start from the actual data of the service:
- number of utilities served;
- quantity collected by fraction;
- frequency of emptying;
- any episodes of overfillment;
- seasonality;
- presence of non-domestic activities;
- any changes foreseen after the intervention.
Where historical data is not available, estimates should be explicitly treated as design assumptions to be checked.
--
2. Type of refusal: not all fractions require the same capacity
The location should be designed for individual fractions, not only for total volume.
Paper, glass, multimaterial, organic and residual waste can have different quantities, conferencing frequencies and apparent density.
This can lead to configurations in which the containers have different volumes while being part of the same island.
Bunder Waste solutions include, for example, 3, 4 and 5 m3 basement bells and semi-internet configurations with different volumes, including specific solutions for organic fraction.
The question to ask is:
**quantity capacity serves for each fraction and not only how much capacity does it serve altogether? * *
This becomes particularly important in tourist municipalities, where waste production can change significantly between high and low season.
--
#3. Volumetric: dimensional the container according to the service
Once you define fractions and utilities, you can address the theme of capacity.
The necessary volumetrics depends at least on:
**provisional production + collection frequency + required operating margin. * *
However, that margin should not be transformed into a standard value for any project.
A station that is emptied every day will have different needs than a designed to collect more quantities between two consecutive steps of the medium.
Also the chosen container must be compatible with the emptying mode.
Indoor vertical bells are available in 3, 4 and 5 m3 configurations, while bin systems use different volumes according to the type of container and platform.
Attention to nominal capacity
The volume stated by the manufacturer is not automatically equivalent to the operating capacity that should be used for the sizing of the service.
It should also be considered:
- maximum permitted filling level;
- frequency of emptying;
- characteristics of refusal;
- method of conferment;
- any operational restrictions;
- criteria used by the operator to programme the service.
This is why the specific technique clearly distinguishes ** nominal volume, container configuration and filling management mode*.
--
#4. Collection Frequency: the container must be sized together with the lap
An ecological island is part of a collection path.
If a station has to be emptied frequently, a smaller volume can be sufficient. If the project aims to reduce the number of interventions, it will be necessary to assess a greater capacity, compatibly with space and technology.
Bunder Waste indicates among the possible advantages of the underground islands the possibility of optimizing the harvest turns, but this should not be considered an automatic result. It depends on the correct size and the actual organisation of the service.
A professional project should therefore explain at least:
**current frequency
expected frequency
required capacity
means used. * *
If these four data are not consistent, the choice of the container is likely to be made in advance of the problem it should solve.
--
#5. Means used: compatibility comes before purchase
It is one of the most important aspects of the entire project.
The technology must be compatible with the means that must carry out the service.
Bunder Waste clearly distinguishes:
- basement bells of 3, 4 and 5 m3, emptiable by means equipped with socket systems and loaders;
- hydraulic trays for 1100 and 1,700 litres, combined with rear loading compactors;
- 2,400 and 3,200 litre stationary bins, combined with side loading compactors.
This report should be checked before setting up the location.
♪ The form to be filled out by means
For the available medium it is advisable to detect at least:
- type of loading;
- socket system;
- encumbrance;
- operating height;
- necessary lateral space;
- necessary rear space;
- any hydraulic connections;
- any control systems;
- operator position during operations.
A real competition can highlight how articulate this relationship between equipment and service. In the AMIU Apulia race for the entire islands of Bari, issues relating to data communication, electronic devices, the management of the bestowal mouths and the precise positioning of the islands appear.
--
#6. Available space: measure above and below the ground
The surface is not enough.
For an underground station, at least:
- area occupied by the structure;
- free area necessary by means;
- position of the towers or of the bestowal vents;
- pedestrian areas;
- necessary space for opening and maintenance;
- depth available;
- subsoil interference.
For interrate pedane, for example, the structure includes cassero, electro-hydraulic system, treadmill, command unit and towers. The dimensions of the cassero vary according to the number and volume of the housings.
So it is not enough to indicate "available area 20 m2". It needs a three-dimensional verification, at least at a preliminary level.
--
#7. Access to vehicles: the truck must be able to work, not only to arrive
A road can be sufficiently wide for the passage of a vehicle but does not allow the necessary operations to empty.
The project should check:
- stop point;
- direction of march;
- space for manoeuvre;
- position regarding the location;
- any need to occupy a lane;
- presence of parking spaces;
- interference with pedestrians and cyclists;
- visibility during operations;
- any temporal limitations to transit.
This criterion becomes particularly important in historical centres.
A chargeable bin platform and a stationary platform do not necessarily require the same method of positioning the vehicle. Bunder Waste in fact indicates the first on narrow streets and historic centres and the second on easy-to-shoe roads.
Operational inspection
A photographic relief should include not only the point where the island will rise, but also:
- at least one incoming view of the middle;
- a view from the service position;
- side access;
- obstacles;
- parking spaces;
- the flooring;
- Any shrinkage.
The question to check on the place is simple:
**Can the vehicle complete the entire operating cycle without creating a situation incompatible with the road? *
--
#8. Security: also design what happens when emptying
Security is not just about the construction site.
An underground station contains mobile parts or technical areas that can become relevant during:
- lifting of containers;
- opening of pedestrians;
- emptying;
- access to the structure;
- maintenance;
- extraordinary interventions.
For the design and implementation of the works, the provisions applicable to health and safety in workplaces and yards must be considered. Legislative Decree 81/2008 also governs temporary or mobile yards and contains specific provisions relating to excavations and foundations. The current text is updated by Normactive in March 2026.
In addition, for underground and semi-integrated stationary containers raised from the top and emptied from the bottom, the UNI EN 13071 series includes safety requirements and indications for installation, maintenance and cleaning; Part 2 specifically concerns underground and semi-integrated systems.
These references do not replace the design of the single installation, but help to define the technical framework to be checked.
--
#9. Civil Works: the island begins long before the container
The visible part of the island is only a portion of the intervention.
Depending on the configuration you may need:
- excavation works;
- preparation of the plan;
- containment structure;
- foundations or backgrounds;
- possible water management;
- laying of the structure;
- electrical or hydraulic connections, when required;
- restoration of the flooring;
- accessories for safety;
- any roadside accommodation.
The AMIU Apulia race published in 2025 is a concrete example of this setting: the object included the supply and installation in operation of underground eco-recycling islands and the documentation included, in addition to the specifications and the technical sheet, also price list and metric compute.
For the RUP or the designer means that the offer request should clarify precisely what is in the supply.
"Island supply" and "full intervention made and tested" are not necessarily the same.
--
#10. Subsoil services and conditions
Before permanently fixing the position of the station it is necessary to check what is located under the road plan.
Among the elements to be mapped can be:
- sewerage;
- aqueduct;
- gas.
- electricity;
- telecommunications;
- technological networks;
- existing artifacts;
- underground structures;
- any archaeological constraints, when relevant.
The verification should be integrated with the site's geometric relief.
It is not enough to know that "there are no interference" on the basis of an unveiled plan.
For real intervention it is appropriate to define which subsoil documentation is available and what verifications are required before the excavation.
Also the documentation of the AMIU Bari race shows how the positioning of the individual islands is an autonomous project question: among the questions published it was asked to specify the place of positioning of the islands because this information was not sufficiently defined in the specifications.
--
#11. Finishes and integration with urban context
Good design does not end when the system works.
The upper floor must be integrated into the existing surface or the one provided for in the project.
For underground pawns, Bunder Waste indicates galvanized and mandored steel treadmills or predisposed to receive a floor chosen according to the operation.
This allows to address the project not only as a plant problem, but also as an urban intervention.
In a historic square it can be necessary to coordinate:
- flooring;
- quotas;
- escapes;
- materials;
- pedestrian accessibility;
- visible elements;
- colors and finishes;
- relationship with existing buildings and furnishings.
The same technology can therefore have a very different urban result depending on how it is integrated.
--
#12. Access control and filling monitoring
Electronic functions must be introduced because they solve a need for service, not simply because they are available.
Bunder Waste indicates that the different configurations of underground, semi-interred and off-ground containers can be completed with hardware and software systems for access control and filling level.
Access control
It can be evaluated when the project requires, for example:
- access reserved for certain users;
- identification of the conferer;
- computerized access management;
- any tariff or control strategies.
It is not necessary in a place where access must remain completely free and there are no identification requirements.
Fill Monitoring
The level sensor can be useful when the data is actually used to arrange the service.
Before inserting it into the specific technique it is therefore necessary to define:
**who receives the data, with which frequency, through which system and which operational decision must support. * *
A AMIU Puglia race of 2025 shows how these specifications can become articulated: in the procedure there were requests regarding the availability of data, the bidirectional communication, the self-diagnosis and the electronic management of the bestowal vents.
The technology should therefore be designed together with the architecture of the service, not added to the end.
--
♪ How to turn checklist into a preliminary project
Once the twelve information groups are collected, the project can be arranged in five blocks.
Block 1: Service question
Define:
- users;
- fractions;
- quantity;
- seasonality;
- frequency;
- Manager's targets.
The result must be a clear estimate of the function the island must perform.
Block 2: collection technology
Define:
- type of container;
- capacity;
- mode of grip;
- lifting system;
- compatible medium;
- emptying mode.
It is here that concretely compare bells and pedane.
Block 3: website
Define:
- position;
- encumbrance;
- depth;
- underservices;
- viability;
- space for manoeuvre;
- pedestrian routes;
- flooring.
The result should be a preliminary layout of the location.
Block 4: works and safety
Define:
- dig;
- structure;
- foundations or backgrounds;
- water management, when relevant;
- restorations;
- site safety;
- safety during the exercise;
- accessibility for maintenance.
Block 5: future management
Define:
- maintenance;
- fault management;
- access control, if required;
- sensors;
- data transmission;
- operational responsibility;
- assistance mode;
- any consumables or components subject to replacement.
--
♪ What technology to evaluate according to the project?
Bunder Waste associates the main configurations with different operating contexts. This classification can be used as a starting point, without turning it into a universal rule.
| Project situation | Configuration to be deepened | ♪ ♪ Urban or semi-peripheral area with high capacity | Indoor bells | ♪ narrow street or historic centre with rear compactor | Pedana for loadable bins | | Easy sliding road with side loading | Pedana for stationary bins | ♪ Extraurban or peripheral area where it can be useful to keep part of the system off ground | Basement system | ♪ Site with excavation difficulties | Preliminary comparison between basement and other configurations | | Posting with user identification need | Configuration for access control | | Service that uses fill data to plan | rpm Configuration prepared for | level monitoring
The table value is not in automatically selecting a product, but in narrowing the field of technology to be subjected to technical verification.
--
♪ What should contain a technical request to a supplier?
A generic request as "preventive for an underground island" leaves too many open variables.
To receive proposals effectively comparable it is useful to prepare a request card containing at least:
Site data
- address and layout;
- photographs;
- area size;
- existing flooring;
- information available on sub-services;
- any urban or architectural constraints.
Service Data
- number and type of users;
- fractions;
- estimated quantity;
- frequencies;
- number of posts provided;
- any seasonal variations.
Fleet data
- model or type of medium;
- rear or lateral loading;
- socket system;
- operational dimensions;
- any connection requirements.
Technology Requirements
- free or controlled access;
- identification of the user;
- filling sensors;
- data transmission;
- remote management;
- any software integrations.
Scope of supply
It is also necessary to clarify whether the supplier should understand:
- equipment;
- structure;
- transport;
- laying;
- civil works;
- links;
- restoration of the flooring;
- testing;
- training;
- maintenance;
- assistance;
- associated software and services.
This is one of the most important points to be defined to avoid formally comparable but substantially different offers.
--
♪ The most frequent design errors
Choose the ability before you know the users
Brings dimensions based on the catalogue instead of the service.
Choose the container before the middle
It claims to generate an incompatible position with the existing fleet.
Consider only the available surface
The volume occupied under the ground can be equally decisive.
♪ Do not study the location of the middle
An island can fit perfectly into the plane and be difficult to serve in real conditions.
Confuse supply and complete work
Equipment, civil works, installation and restoration can belong to different items of supply.
Insert smart systems without defining the process
A sensor is useful when the data enters an operating process. Without this connection it simply becomes an additional component to maintain.
##Return maintenance to next stage
The position of components, accesses and mode of intervention should be defined already in design.
♪ Do not check the urban context
In squares, historic centres and valuable areas the outside ground and finishes can be as decisive as the technology below.
--
♪ Final checklist for Municipality, designer and RUP
Before approving a preliminary configuration, the following questions should have a documented answer.
Service
- How many users will be served?
- What fractions will be collected?
- What quantities are expected?
- What frequency of emptying is expected?
Technology
- What container is it?
- What capacity?
- What system?
- What emptying mode?
♪ Starfleet
- What means will the collection take?
- Is it already available?
- Is it compatible with the container?
- What space does it need during operations?
♪
- Where exactly will the island be located?
- What do you have?
- What depth is available? Did the subservices check?
- Can the medium reach it and work correctly?
- What excavations are necessary?
- What structure should be realized?
- How are any interference handled?
- How is the pavement restored?
Security and maintenance
- How is emptying done?
- What parts are handled? How do you access maintenance?
- How is a failure handled?
Do you need access control? Do you need user identification?
- Do you need filling monitoring?
- Where do they converge and how do data be used?
Supply
- Who makes civil works?
- Who does the laying?
- Who is testing?
- What is included in maintenance?
- What components or services remain to the manager?
When these questions are defined, the choice of technology becomes much more concrete.
See the dedicated guide on procurement and delivery for underground eco-islands for a checklist that separates equipment supply, installation, civil works and service management.
♪ From checklist to specific technique
For a public project or for a complex supply, the final result should not only be a product description.
The documentation should come at least to define:
**function of the post
capacity
configuration
collection system
compatible media
encumbrance
civil works
security
management
possible digital technology. * *
It is this sequence that allows the Municipality, the designer, the RUP and the supplier to talk about the same object.
A 2025 AMIU Apulia race for the islands of Bari is a concrete example of the need for articulated documentation: in addition to the procedure of competition, they were available disciplinary, capitulate, technical sheet of containers, price list and metric compute. The race was expressly concerned with the ** supply and installation** of the islands.
The design of an underground station should follow the same logic, adapted to the size and complexity of the intervention.
♪ The ecological island is an infrastructure of the collection service
The container is only part of the system.
A truly usable project must run together users, containers, infrastructure, road, means, operators and subsequent management.
This is why the preliminary phase is so important: a wrong choice on the volumetrics can create filling problems; a wrong choice on the medium can make the post unusable; an incomplete verification of the subsoil can change the project; a unclear specification on the supply can generate difficult to compare offers.
Technology comes after the definition of the problem.
To deepen the available configurations, you can consult the section dedicated to the interrate ecological suns, compare the float underground containers or deepen the *components of the bins.
FAQ
♪ What data do you need to design an underground eco-recycling island?
We need at least information about utilities, fractions collected, expected quantities, frequency of collection, available means, position of the station, space on the surface and underground, accessibility, civil works and management modes. Any access control or monitoring systems must be defined separately.
How many cubic metres do you need for an ecological island?
There is no standard volume valid for any project. The capacity must be dimensioned according to the utilities, quantities for each fraction, frequency of emptying, seasonality and system configuration.
♪ Should the harvest be chosen before the island?
Compatibility with the vehicle must be verified in the early stages of the project. The different configurations have different gripping and emptying modes: for example, the loadable bins are associated with the rear loading, while the stationary platforms are associated with the side loading.
How does it occur if the medium can serve the island properly?
You need to check the stop point of the vehicle, the operating encumbrances, the lateral or rear space required, the maneuvers, the presence of obstacles and interference with traffic and pedestrians. The nickname should simulate the actual emptying sequence.
♪ What civil works do you need for an underground island?
It depends on the configuration and the site. Excavation works, floor preparation, containment structures, possible water management systems, laying, links and floor restoration can be required. The supply of the equipment does not necessarily coincide with the complete realization of the intervention.
♪ What norms do underground containers apply?
For stationary containers raised from above and emptied from below, the UNI EN 13071 series includes general requirements and additional requirements for underground and semi-interred systems. Part 1:2019 is in force and Part 2:2019 is specifically concerned with underground or semi-interrate systems. In addition, the relevant provisions of Legislative Decree 81/2008 and of the related legislation apply to construction and excavation activities.
♪ Is it necessary to check the subservices before designing the island?
Yes, the position of the location must also be assessed in relation to the infrastructure in the subsoil. An unregistered floor plan should not be considered sufficient to define the definitive position of a dig alone.
When should I predict access control?
When there is a real need to identify or limit users, or when the service model provides for computerized management of the contributions. It is not a necessary function for each location.
When should I install filling sensors?
When the fill level data is used to make operational decisions, such as programming interventions or monitoring the status of stations. Before inserting them into the capitulate it is therefore useful to define who will use the data and through which system.
♪ Is it possible to use the pavement of the square over the island?
It depends on the configuration of the platform and the project. Some solutions include a floor plan prepared to receive a floor chosen according to the intervention. Compatibility must be verified with the specific system.
♪ What should a quote request contain?
It should describe at least site, planimetry, utilities, fractions, required capacity, collecting frequency, available means, grip modes, required civil works and optional technologies. It is also important to clearly indicate what should be included in the supply.
Final CTA
If you are designing a new underground eco-recycling island, starting from the technology can create constraints too early.
It is more useful to define users, waste streams, capacity, frequency, vehicles, site and required works first, then compare the configuration most aligned with the project.
Explore underground eco-recycling island solutions and the related technical configurations. Contact Bunder Waste for project-specific guidance.
Products that may fit your project
For projects like yours, many Bunder Waste customers start with these solutions. Compare capacity, use case and configurations before you get in touch for a quote.

Sotkon · APTO
Underground bell-shaped containers
Sotkon’s APTO system, distributed in Italy by Bunder Company SRL under Bunder Waste, holds 3 to 5 m³ below grade with a monolithic shell, hot-dip galvanised st…
View product
Sounete · Back
Pedane per cassonetti carrellati
Sounete Back hydraulic platforms, distributed in Italy by Bunder Company SRL, bury two to four wheeled bins: MRT chutes at street level, waste below grade and…
View product
Sounete · Side
Underground systems for stationary bins
Sounete Side buries one or two 2,400 or 3,200 litre containers (up to 4,000 L in dedicated setups) in a concrete shell: scissor cover, hydraulic lift and empty…
View product
Traflux · ZBin
Semi-underground polyethylene containers
Semi-underground and above-ground polyethylene bell units for source-separated collection: configurable with internal bag, PE tub or steel liner, capacities up…
View product
Traflux · RBin
Modular semi-underground containers
RBin 2.0 is the high-volume semi-underground unit in the Traflux line (made in Belgium, supplied in Italy through Bunder Waste): reinforced concrete pit, compa…
View product
Telemetry · Bunder Waste
Fill-level sensors
Fill-level sensors measure how full each island node is in near real time: they show which points to empty first, flag overflow risk early and send vehicles on…
View product